Section 5.01 of Notice 2013-29 provides the Five Percent Safe Harbor:
- Construction of a facility will be considered as having begun before [the statutory deadline] if (1) a taxpayer pays or incurs (within the meaning of Treas. Reg. ยง 1.461-1(a)(1) and (2)) five percent or more of the total cost of the facility, except as provided in section 5.01(2), before [the statutory deadline] and (2) thereafter, the taxpayer makes continuous efforts to advance towards completion of the facility (as determined under section 5.02).
Section 5.02(1) of Notice 2013-29 provides that whether a taxpayer makes continuous efforts to advance towards completion of the facility will be determined by the relevant facts and circumstances (Continuous Efforts Test). This section also provides that facts and circumstances indicating continuous efforts to advance towards completion of the facility may include, but are not limited to:
- (a) paying or incurring additional amounts included in the total cost of the facility;
- (b) entering into binding written contracts for components or future work on construction of the facility;
- (c) obtaining necessary permits; and
- (d) performing physical work of a significant nature.
Notice 2013-60 clarifies certain concepts provided in Notice 2013-29. Notice 2013-60 provides a Continuity Safe Harbor that allows a facility to be deemed to have satisfied the Continuity Requirement. Section 3.02 of Notice 2013-60 provides that if a facility is placed in service before January 1, 2016, the facility will be considered to satisfy the Continuous Construction Test (for purposes of satisfying the Physical Work Test) or the Continuous Efforts Test (for purposes of satisfying the Five Percent Safe Harbor). Section 3.02 of Notice 2013-60 also provides that if a facility is not placed in service before January 1, 2016, whether the facility satisfies the Continuous Construction or Continuous Efforts Tests will be determined by the relevant facts and